With the holidays behind us, work has continued to spread out throughout the entire project area during the month of January.

Widening has begun on I-26 Eastbound just past the Remount Road interchange.

 


 


Work is continuing on the new exit ramp from I-26 Eastbound at Remount Road.

 

 
 


As part of the Remount Road realignment, the new Casper Pagent Way is nearing completion.  


 


Work on the Remount Road overpass structure continues.  The eastbound side is nearly done, and the westbound side approaches are underway.  

 


Restriping and shifting of the lanes of both directions of I-26 is underway.  This is intended to prepare for construction of the center lanes and median.  


Storm drainage work along Fain Boulevard is burying the open ditches to prepare for work on the roadway.  


Work on the new entrance ramp onto I-26 Westbound at Remount Road is making considerable headway.

 

  
 


 

 